• Home
  • Download PDF
  • Order CD-ROM
  • Order in Print
FIGURE 7-4A.--EQUIPMENT IMPROVEMENT PROGRAM, MAJOR MILESTONES
Figure 7-5B.-Funding plan (DART) (explanation for using chart).

Engineering Administration - Administrative Structural engineering guide book
Page Navigation
  136    137    138    139    140  141  142    143    144    145    146  
Figure  7-4B.-Equipment  improvement  program,  major  milestones  (Instructions  for  using  chart). 2. A major milestone plan (see fig. 7-4) You may want to use separate plans to identify milestones   for   major   independent   efforts.   As   an example, make one plan to procure an improved design and another plan to improve existing technical manuals. 3. Funding plan (see fig. 7-5, views A and B) The implementation and major milestone plans should project the best reasonable solution assuming ideal funding. The funding plan should then show fund deficits,  if  any,  between  those  available  and  those required   for   the   recommended   solution.   The responsible  SYSCOM  or  PM  should  try  to  resolve funding  deficits  in  the  current  fiscal  year,  without compromising  the  solution,  and  before  he  submits  the proposal  to  the  DPD.  After  the  DPD  reviews  the program,  the  SYSCOM  or  PM  must  remove  any funding   deficit   for   the   following   fiscal   years   by reprogramming   funds. The   improvement   program   for   each   DART equipment must be submitted to the DPD as soon as possible, but not later than 90 days after the equipment has been approved for DART by CNM. The  DEM  will  brief  the  DPD  on  the  submitted improvement plan upon request. At that time, the DEM should  be  prepared  to  address  the  time,  cost,  and improvement goals of alternative solutions. The DEM should be sure that the improvement program he discusses with the DPD is backed up by a detailed  management  plan.  That  plan  should  include detailed  milestone  and  funding  information  for  studies, tests,  procurements,  installation  schedules,  and  actions related  to  integrated  logistic  support  (ILS). Progressing   Phase In  the  progressing  phase,  the  SYSCOM  or  PM submits the following plans quarterly on colitho mats or 7-11







Western Governors University

Privacy Statement
Press Release
Contact

© Copyright Integrated Publishing, Inc.. All Rights Reserved. Design by Strategico.