4-32.
4-33.
4-34.
4-35.
4-36.
4-37.
Which of the following factors
should NOT be included in project
specifications?
1.
Quality of materials
2.
Workmanship standards
3.
Crew sizes
4.
Description of materials
The project supervisor should take
which of the following actions when
conflicts occur between the project
drawings and the specification?
1.
Comply with the drawings
2.
Comply with the specifications
3.
Obtain guidance from S-3
4.
Obtain guidance from the ROICC
A contractor desiring to bid on
a government construction project
should find specific bidding
requirements in what division
of the project specifications?
1.
1
2.
10
3.
3
4.
13
The quality of all lumber to be
used in a project is specified
under what division of project
specifications?
1.
10
2.
8
3.
6
4.
4
What division of the project
specifications will normally
specify the gauge of metal to
be used for HVAC ductwork?
1.
5
2.
7
3.
13
4.
15
The type of materials used in a
plumbing system should be specified
in what part of the division
dealing with plumbing?
1.
1
2.
2
3.
3
4-38.
4-39.
4-40.
4-41.
4-42.
The specified fastening method for
ceiling installation of gypsum
wallboard should be identified in
what part of the Finishes division
of the project specifications?
1.
1
2.
2
3.
3
To save time and effort, you should
make reference to NAVFAC and EFD
guide specifications in the project
specs. This is a common and
accepted practice of spec writers.
1.
True
2.
False
Learning Objective:
Define
terminology and describe technigues
used in material estimating.
Which of the following qualities is
required to be a good estimator?
1.
Sound construction knowledge
2.
Knowledge of material
estimating procedures
3.
Knowledge of material
estimating pitfalls
4.
Each of the above
When a conflict exists between the
general drawing and a detail, which
drawing, if either, should you
follow?
1.
General always
2.
Detail unless it is obviously
wrong
3.
Detail always
4.
Neither, contact the drafter
What step should the estimator do
first when starting an estimate?
1.
Review the drawings
2.
Read NAVFAC P-405
3.
Study the specifications
4.
Make a rough estimate from
the drawings
25