Textbook Assignment:
Direct
14-47.
A S S I G N M E N T
12
Leveling and Basic Engineering Surveys.
Pages 14-25 through
12-1.
Fieldwork on the construction of a
road being built on a 5-year-old
naval air station would very likely
begin with what type of survey?
1.
Final location
2.
Topographic
3.
Reconnaissance
4.
As-built
12-2.
What is the first step in a
reconnaissance survey?
1.
A field trip to the desired
location
2.
A study of existing maps and
aerial photographs
3.
An instrument survey of the
desired location
4.
An inventory of available
construction equipment
12-3.
Direct air observation of an area
to be reconnoitered offers what
main advantage?
1.
Acquiring information about
the relief of the area
2.
Providing a quick means of
preparing sketches of the area
3.
Speeding subsequent ground
reconnaissance of the area
4.
Providing a quick means of
preparing maps of the area
12-4.
A field reconnaissance party
follows the route previously marked
on a map to verify actual
conditions on the ground.
Which of
the following conditions, relative
to an engineering study, should be
noted?
1.
Soil conditions and washout
areas
2.
Vegetation and obstacles
3.
Quarry sites and sand or
gravel deposits
4.
All of the above
12-5.
Which of the following tasks in
constructing a highway is part of
the preliminary survey?
1.
Establishing final grades and
alignments
2.
Computing the highway
right-of-way
3.
Running the traverse
4.
Setting grade stakes
12-6.
Your survey party is assigned the
task of completing a reconnaissance
survey of a 3-mile road in hilly,
wooded terrain.
For this survey,
your party should carry which of
the following equipment?
1.
Lensatic compass
2.
Brush hook
3.
Hand level
4.
All of the above
12-7.
As the lead surveyor laying out the
final location of a roadway center
line, you suspect that the
preliminary survey was in error
regarding the exact location of the
center line.
Which of the
following actions should you take?
1.
Lay out the center line
according to the preliminary
data
2.
Lay out the center line the
way you know it should be
3.
Lay out the center line and
then report the reason for
making the necessary change
4.
Report the problem and receive
authorization before making
the location change
12-8.
Which of the following details must
be shown on a plan view of a
proposed highway?
1.
Curve design data
2.
Gradient
3.
Spot elevations
4.
Typical cross section of the
highway
12-9.
When plotting a profile, you should
use which of the following
(a) horizontal and (b) vertical
scales?
1.
(a) 1" = 200 (b) 1" = 20
2.
(a) 1" = 20 (b) 1" = 200
3.
(a) 1" = 135 (b) 1" = 15
4.
(a) 1" = 205 (b) 1" = 20
82