Figure 14-7.Example end-of-month status for a project.
Q3. Figure 14-7 shows the end-of-month status for a
Seabee project. For this project, what is the total
percent of project completion that should be
reported in the monthly SITREP? (You will need
to determine the missing data)
Q4. A certain NCF project was originally estimated
to require 600 man-days of direct labor. To date,
650 man-days have been expended and the
project is 75-percent complete. Based on this
information only, how many man-days of labor
should be required to complete the remaining 25
percent of the project?
14-14
Q5. Assume that your battalion is deployed to Seabee
Camp Shields, Okinawa. As part of your
engineering tasking for the deployment, you are
to prepare construction drawings for a future
project to be sited at the camp. When completed
to what command should the drawings be
forwarded for final approval?
Q6. According to the TRAMAN, there are two
reasons for you to have the ability to foresee all
of the steps required to complete a job that you
intend to assign to one of your EAs. What are
those two reasons?