Figure 14-7.—Example end-of-month status for a project.Q3. Figure 14-7 shows the end-of-month status for aSeabee project. For this project, what is the totalpercent of project completion that should bereported in the monthly SITREP? (You will needto determine the missing data)Q4. A certain NCF project was originally estimatedto require 600 man-days of direct labor. To date,650 man-days have been expended and theproject is 75-percent complete. Based on thisinformation only, how many man-days of laborshould be required to complete the remaining 25percent of the project?14-14Q5. Assume that your battalion is deployed to SeabeeCamp Shields, Okinawa. As part of yourengineering tasking for the deployment, you areto prepare construction drawings for a futureproject to be sited at the camp. When completedto what command should the drawings beforwarded for final approval?Q6. According to the TRAMAN, there are tworeasons for you to have the ability to foresee allof the steps required to complete a job that youintend to assign to one of your EAs. What arethose two reasons?
Integrated Publishing, Inc. - A (SDVOSB) Service Disabled Veteran Owned Small Business