other existing utilities, there should be existing
utilities maps that can be used in the design of the new
utility line. Consequently, in cases such as this,
reconnaissance and preliminary surveys are seldom
necessary. On the other hand, a power transmission
line or other utility running through open country on
a large military installation may require reconnais-
sance and preliminary surveys in addition to the final-
location survey.
For discussion purposes, lets consider route
surveys for overhead electrical lines.
Route Surveys for Overhead Electrical
Distribution and Transmission Lines
The reconnaissance survey for electrical power
lines employs many of the same principles and
practices that you studied for highway work; however,
the design considerations are different. For a power
line, the design engineer considers principles that you
studied in chapter 2 of this TRAMAN to select one or
more tentative routes over which the line will pass. For
convenience, those principles are listed as follows:
1. Select the shortest possible route.
2. Follow the highways and roads as much as
possible.
3. Follow the farmers property or section lines.
4. Route in the direction of possible future loads.
5. Avoid going over hills, ridges, swamps, and
bottom lands.
6. Avoid disrupting the environment.
During the reconnaissance phase, you should first
study all available maps of the area to gain a general
understanding of the landscape. If a portion of the line
is off the military installation, determine the owner-
ship of the lands through which the line will pass. That
is necessary to obtain permission to run the line. Look
for any existing utilities that may already exist in
the area. If there are existing utilities, then look for
existing utilities maps. Visit the area to examine the
terrain and look for any natural or man-made features
that may hinder or help the construction. In short,
gather all information that the engineer will need to
select one or more general routes for the power line.
With the tentative route or routes selected, you are
ready to conduct a preliminary survey from which a
map is prepared showing the country over which the
line will pass. Since the final location is not known, a
wide strip of land needs to be mapped. When running
the preliminary survey, incorporate all pertinent
topographic information into the field notes. Note
particularly any existing overhead or underground
lines and indicate whether they are power or
communications lines. Locate such features as hills,
ridges, marshes, streams, forests, roads, railways,
power plants, buildings, and adjacent military camps
or bases.
When the preliminary mapping is completed, the
engineer selects the final route. Again, the engineer
considers the principles listed above to select the
route.
POLE LINE SURVEYS. When the route has
been selected, a plan and profile are plotted. The plan
shows the route the line will follow and the significant
topography adjacent to the route. The profile shows
the ground elevation along the line and the top eleva-
tions of the poles. These elevations are set in accord-
ance with minimum allowable clearances specified in
the National Electrical Safety Code (NESC), ANSI
C2, and the most recent edition of the National
Electrical Code® (NEC®).
For distribution lines, poles should be placed on
the side of the street that is most free of other lines and
trees. Try to keep off the main streets. As much as
possible, you should use the same side of the road
throughout the length of the line. For straight portions
of lines, the usual spacing between poles is about 125
feet (100 feet minimum and 150 feet maximum);
however, to make the poles come in line with property
lines or fences, the span length may need to be
adjusted. The engineer will determine the spans.
Along roads, poles should be placed 2 feet from the
inside edge of the curb or 2 feet from the edge of the
road surface where curbs do not exist. On open
roadways or highways, poles should be set 18 inches
from the outside of fences.
For transmission lines, poles should be located in
high places so that shorter poles can be used and still
maintain the proper ground clearance at the middle of
the span. Avoid locating poles along the edge of
embankments or streams where washouts can be
expected. In rolling country, the grading of the line
should be considered when determining pole
locations. A well-graded line does not have any abrupt
changes up or down the line and will appear nearly
horizontal regardless of small changes in ground level.
Sometimes, by shifting a pole location a few feet, a
standard length pole can be used where otherwise an
odd-sized pole would be needed. In addition,
transmission line poles should be located at least 2 feet
10-2